You can edit text on your website by double clicking on a text box on your website. Alternatively, when you select a text box a settings menu will appear. Selecting 'Edit Text' from this menu will also allow you to edit the text within this text box. Remember to keep your wording friendly, approachable and easy to understand as if you were talking to your customer

Heading 3

Vista Peak High School

E17025
GENERAL INFORMATION:
Vista Peak High School

Address:
24500 E. 6th Ave.
Aurora, CO 80018

The present work schedule is:
Start Time: 6:00AM
Break Time: 9:30 AM
Lunch: 12:00PM - 12:30PM
Cleanup: 2:20PM
End Time: 2:30 PM

PLEASE NOTE ALL EMPLOYEES MUST HAVE THEIR DRUG SCREEN CHAIN OF CUSTODY IN ORDER TO ENTER THE SITE FOR ORIENTATION.

Start times are in your assigned work area with your tools on! 
Quitting times are leaving your work area. 
Pick up is 10 minutes before quitting time & everyone helps everyone else.
9 Panel Drug Screen & Orientation are required prior to access to the site.

REMEMBER:  WE ARE A TEAM!


SPECIAL INSTRUCTIONS AND INFORMATION

.



All employees are required to visit this website for information updates. We will use this website to broadcast the latest information regarding weather and job-related announcements. 

PLEASE CHECK OFTEN FOR THE LATEST INFORMATION






PLEASE DO NOT ASSUME SITE WORK IS SHUT DOWN DUE TO WEATHER> ALWAYS CHECK HERE FOR INFORMATION OR CALL YOUR SUPERVISOR TO CONFIRM

PLEASE BE AWARE OF SURROUNDINGS AT ALL TIMES.
EVERY 30 MINUTES, TAKE 30 SECONDS AND LOOK AROUND 30 FEET AND LOOK FOR HAZARDS

ALWAYS KNOW THE ADDRESS WHERE YOU ARE AND ALWAYS KNOW YOUR EVACUATION ROUTE OUT OF A BUILDING
 

SAFETY
SDS ARE LOCATED IN: THE SUPERINTENDENTS TRUCK

All Accidents and injuries mus tbe reported immediately.
CALL Ted Smith 303-550-5292
If you get a voice mail, hang up and call again immediately and the phone will be answered.
 

CONTACT INFORMATION:

CONTACT INFORMATION:
Project Manager: Ryan Dobson 720-483-5632
Job Contact: Kent Perri 303-921-0774
Project Coordinator: Ally Nelson 303-952-1124
For Safety: Ted Smith 303-550-5292
*For Absences/Tardies Please Call: 303-921-0774*



















JOBSITE RULES, RESTRICTIONSPROJECT INFORAMTION

Safety BALANCE OF PRIORITIES

We need to all remember that Safety, Productivity, and Quality are all important in order for us to complete our work, make the company profitable so that we can continue to be competitive and go home to our friends and family. Each employee should be constantly evaluating what they are doing and balancing those priorities. Remember: 30-30-30/ Every 30 minutes, stop for 30 seconds, look around 30 feet and understand what is around you.

Report ANY unsafe conditions to your supervisor. We will adhere to all company & safety policies, also OSHA standard in temporary electric & general safety requirements.

Report ALL injuries to your FOREMAN or project supervisor IMMEDIATELY

Housekeeping/clean-up will be required for ALL employees on a daily basis.

Each employee will have a current pretask card on their person at all times while on duty and the corporate challenging policy will be followed.


ALL SAFETY POLICIES ARE ENFORCED ON THIS SITE!
All employees will be required to take a drug screen.


Safety glasses, hard hats, and warning vests are to be worn at all times on the job site.
100% natural fiber clothing is recommended and sleeves must go to at least the elbow. Boots with safety toes are also required.

Energized work may only be done by qualified personnel after an Energized Work Permit has been approved by site management and the Director of Education and Loss Prevention.


Keep personal tools on site or in gang boxes at your own risk.

All tools need to be returned to carrying cases, along with their accessories and operators manual and placed in the gang box in their cases.

Gang boxes need to be kept closed and unused tools put away.



SOME INSTALLATION PARTICULARS:
Color Codes:
120/208V 3 phase 4 wire:   277/480V 3 phase 4 wire:
Black Brown
Red   Orange
Blue   Yellow
White Gray
Green     Green
All work will only be done once and must look good.
It is understood that any inappropriate action (i.e., whistling, catcalling, etc.), is grounds for immediate dismissal from the project for its duration.
No member of the Contractor or Subcontractor’s personnel is allowed to communicate with any member of any type of media about this project. All requests for a response to the media are to be directed to the Contractor’s Project Manager or Superintendent, who will elevate the request to the General Contractor.
If you have any questions, or you are not sure about something, stop and ask.  Mistakes cost money and waste time.

THINK SAFE & WORK SAFE!
The emergency telephone number is 911.

RECORD DOCUMENTS:
During construction, the contractor shall maintain at the job site a set of updated construction documents for the singular purpose of recording changes as the job progresses.  All record drawings shall be completed in erasable pencil.  These changes shall be updated weekly.
Revisions to the Contract Documents shall be legible and shall be prepared using the following color scheme:
1. Red shall indicate new items, deviations, and routing.
2. Green shall indicate items removed or deleted.  DO NOT USE WHITE-OUT!
3. Blue shall be used for relevant notes and descriptions.
Your foreman will provide you with the following: tools, materials, layout & a safe work environment. If you feel you are missing any of these items, see the foreman personally. 
​​