E24085 - TMCA Imaging CT
Job #: E24085
Job Name: TMCA Imaging CT
Job Address: 1501 Potomac St., Aurora, Co. 80012
Job Phone #: 720-990-0514
Job Fax #: N/A
Project Superintendent: Tyler Ball Cell: 720-990-0514
Project Manager: Aaron Martinez Cell: 303-819-9160
Project Coordinator: Kayla Van Eyzeren Phone: 303-991-7108
Director of Education and LP: Ted Smith 303-550-5292
Safety Superintendent: Todd Kreps 720-948-7842
WORK TIMES:
Start Work: 6:00 am
Break Time: 9:15-9:30 am
Lunch: 12:00-12:30 pm
Break Time: 1:30-1:45 pm
Quitting Time: 2:30 pm
Start times are in your assigned work area.
Quitting times are leaving your work area.
No on picks up more than 10 minutes before
Quitting time and everyone helps everyone else.
Remember: We are a TEAM.
JOBSITE INFORMATION SHEET
Job #: E24085
Job Name: TMCA Imaging CT
Job Address: 1501 Potomac St., Aurora, Co. 80012
Job Phone #: 720-990-0514
Job Fax #: N/A
Project Superintendent: Tyler Ball Cell: 720-990-0514
Project Manager: Aaron Martinez Cell: 303-819-9160
Project Coordinator: Kayla Van Eyzeren Phone: 303-991-7108
Director of Education and LP: Ted Smith -303-550-5292
Safety Superintendent: Todd Kreps -720-948-7842
WORK TIMES:
Start Work: 6:00 am
Break Time: 9:15-9:30 am
Lunch: 12:00-12:30 pm
Break Time: 1:30-1:45 pm
Quitting Time: 2:30 pm
Start times are in your assigned work area.
Quitting times are leaving your work area.
No on picks up more than 10 minutes before
Quitting time and everyone helps everyone else.
Remember: We are a TEAM.
SAFETY COMES FIRST - Report any unsafe condition to your supervisor. We will adhere to all company and safety policies, also OSHA standards in temporary electric and general safety requirements.
Report ALL injuries to your FOREMAN or project Supervisor immediately.
Housekeeping /clean-up will be required by all employees on a daily basis.
Safety glasses, hard hats and warning vests are to be worn at all times on the jobsite.
100% natural fiber clothing is recommended, and sleeves must go to at least the elbow.
ALL SAFETY POLICIES ARE ENFORCED ON THIS SITE.
SDS information is available Job Site Trailer.
Safety Glasses and hard hats (Type II Class E) are to be worn at all times on the jobsite.
PLEASE NOTE ALL EMPLOYEES MUST HAVE THEIR DRUG SCREEN CHAIN OF CUSTODY IN ORDER TO ENTER THE SITE FOR ORIENTATION.
Job Site Orientation is 7:30am on the first day, employees are expected to be there at least 15 minutes early and employees are expected to report to the superintendent.
NO HOT WORK.
Keep personal tools on site or in gang boxes at your own risk.
All tools need to be returned to carrying cases.
Gang boxes need to be kept closed and unused tools put away.
Call Jobsite at 720-990-0514 if sick or late prior to start work time.
Safety meetings are at office trailer on Wednesday Mornings
SOME INSTALLATION PARTICULARS:
All conductors to be labeled at all boxes.
Provide #10 AWG conductors where distance from panel to first outlet is 75’ or greater for 120V circuits or 200’ or greater for 277V circuits.
All data and phone stub to ceiling.
Mounting Heights:
Panelboards 6’ to top.
Outlets 18” MT center U.O.N. (unless otherwise noted). Vertical with ground at bottom.
Switches – 48” center U.O.N.
Wall phones – 4’6” center U.O.N.
Fire Alarm pull stations - 48” center
Exit lights and fixture heights need to be verified
Color Codes:
120/208V 3 phase 4 wire: 277/480V 3 phase 4 wire:
Black Brown
Red Orange
Blue Yellow
White Gray
Green Green
All work will only be done once and must look clean.
It is understood that any inappropriate action (i.e., whistling, cat calling, etc.), is grounds for immediate dismissal from the project for its duration.
No member of the Contractor or Subcontractor’s personnel is allowed to communicate with any member of any type of media about this project.
All requests for response to the media are to be directed to the Contractor’s Project Manager or Superintendent, who will elevate the request to the General Contractor.
The use of and posting to social media on or about the project is prohibited.
If you have any questions, or you are not sure about something, stop and ask. Mistakes cost money and waste time.
THINK SAFE & WORK SAFE
The emergency telephone number is 911.
Record Documents:
· During construction, the contractor shall maintain the job site a set of updated construction documents for the singular purpose of recording changes as the job progresses.
· All record drawings shall be completed in erasable pencil, these changes shall be updated weekly.
Revisions to the Contract Documents shall be legible and shall be prepared using the following color scheme:
1. Red shall indicate new items, deviations, and routing.
2. Green shall indicate items removed or deleted. Do not use white-out.
3. Blue shall be used for relevant notes and descriptions.
Your foreman will provide you with the following: tools, materials, layout and a safe work environment. If you feel you are missing any of these items, see foreman personally.
ALL ENERGIZED WORK MUST BE DONE BY QUALIFIED PERSONNEL AFTER RECEIVING WRITTEN APPROVAL FROM ALL OF THE FOLLOWING:
1. Construction Manager
2. Project Manager
3. Department Director
4. Director of Education and Loss Prevention