Address: 361 Inverness Drive South, Suite B, Englewood, CO 80112
The present work schedule is: Monday thru Friday
Start Time: 7:00 AM
Break: 8:30AM-8:40AM
Lunch: 12:30 PM-12:30 PM
Break: 2:00- 2:10 PM
Clean-Up: 3:15 PM
End Time: 3:30 PM
Start times are in your assigned work area with your pretask card and ready for stretch and flex and JHA briefing.
Quitting times are leaving your work area.
Pick-up is 15 minutes before quitting time & everyone helps everyone else. All tools must be returned to their case or shadow wall.
REMEMBER: WE ARE A TEAM!
If we are storing material that is not for an active prefabrication order, we are doing wrong.
Please remember A place for everything and everything in its place.
GENERAL INFORMATION:
Address: 361 Inverness Drive South, Suite B, Englewood, CO 80112
The present work schedule is: Monday thru Friday
Start Time: 7:00 AM
Break: 8:30AM-8:40AM
Lunch: 12:30 PM-12:30 PM
Break: 2:00- 2:10 PM
Clean-Up: 3:15 PM
End Time: 3:30 PM
Start times are in your assigned work area with your pretask card and ready for stretch and flex and JHA briefing.
Quitting times are leaving your work area.
Pick-up is 15 minutes before quitting time & everyone helps everyone else. All tools must be returned to their case or shadow wall.
REMEMBER: WE ARE A TEAM!
If we are storing material that is not for an active prefabrication order, we are doing wrong.
Please remember A place for everything and everything in its place.
SPECIAL INSTRUCTIONS AND INFORMATION
All employees are required to visit this website for information updates. We will use this website to broadcast the latest information regarding weather and job-related announcements.
PLEASE CHECK OFTEN FOR THE LATEST INFORMATION
SPECIAL NOTICES:
Thank you
PLEASE DO NOT ASSUME SITE WORK IS SHUT DOWN DUE TO WEATHER> ALWAYS CHECK HERE FOR INFORMATION OR CALL YOUR SUPERVISOR TO CONFIRM
PLEASE BE AWARE OF SURROUNDINGS AT ALL TIMES.
EVERY 30 MINUTES, TAKE 30 SECONDS AND LOOK AROUND 30 FEET AND LOOK FOR HAZARDS
ALWAYS KNOW THE ADDRESS WHERE YOU ARE AND ALWAYS KNOW YOUR EVACUATION ROUTE OUT OF A BUILDING
CONTACT INFORMATION:
Project Manager: Serge Gregoire 720-473-3145
Prefab Logistics: David Garner 719-640-8849
Director E and LP: Ted Smith 303-550-5292
Safety Superintendent: Todd Kreps 720-948-7842
If you are going to be late or absent, you must CALL, NOT TEXT, Serge Gregoire to let him know. 720-473-3145.
If you are not ready to work at start time when Serge starts the Stretch and Flex, you are not allowed to work unless you called Serge Gregoire and let him know you were running late.
If you do not call Serge Gregoire, an absence will be considered a No Call No Show.
ACCIDENTS/ INJURIES
SDS SHEETS ARE LOCATED:
________In the Shop at the Sign in Counter_______
Injuries must be reported immediately.
CALL Ted Smith 303-550-5292
If you get a voice mail, hang up and call again immediately and the phone will be answered.
JOBSITE RULES, RESTRICTIONS, PROJECT INFORAMTION
SAFETY BALANCE OF PRIORITIES
We need to all remember that Safety, Productivity, and Quality are all important in order for us to complete our work and make the company profitable so that we can continue to be competitive and go home to our friends and family.
Each employee should be constantly evaluating what they are doing and balancing those priorities.
Remember: 30-30-30/ Every 30 minutes, stop for 30 seconds, look around 30 feet and be AWARE of your surroundings.
Report ANY unsafe conditions to your supervisor. We will adhere to all company & safety policies, also OSHA Standards for temporary electric & general safety requirements.
Report ALL injuries to your FOREMAN or project supervisor IMMEDIATELY
Housekeeping/clean-up will be required by ALL employees on a daily basis. Everything must be returned to its place and floors swept and the outside entrance area swept. The printer and large screen must be covered, and all tables cleared and organized.
Each employee will have a current pre-task card on their person at all times while on duty and the corporate challenging policy will be followed.
At the end of each shift or task, all trash must be picked up and thrown away, all tools must be returned to their case or their shadow wall. NO EXCEPTIONS. All floors swept, all trash cans emptied, and the back area picked up and swept up. The kitchen wiped down and the coffee pots turned off and placed in the dishwasher and the dishwasher ran.
All tools must be returned to their storage location and put back in their cases.
Safety glasses and warning vests are to be worn at all times on the job site.
100% natural fiber clothing is recommended, and sleeves must go to at least the elbow.
Footwear must be sturdy work boots.
Be sure to park by backing into the parking space. Parking is allowed on the north side of 359 Inverness and the on the west side of 359 Inverness and 361 Inverness. Do not park on the south side or east side of 361 Inverness.
ALL ENERGIZED WORK MUST BE DONE BY QUALIFIED PERSONNEL AFTER RECEIVING WRITTEN APPROVAL FROM ALL OF THE FOLLOWING:
Superintendent
Project Manager
Department Director
Director of Education and Loss Prevention
Keep personal tools on-site or in gang boxes at your own risk. Your personal tools are not covered by E Light's insurance; we recommend you take your personal tools home with you each night.
All company-supplied tools need to be returned to carrying cases before being placed in the gang box for storage each day.
Gang boxes need to be kept closed and unused tools put away.
Stretch and Flex shall be conducted before each work shift.
There is a place for everything and everything has its place. You are responsible for putting everything back in its place when you are done with it.
Do not leave empty or partially full bottles of water laying around.
Do not do work assigned by you without a JHA briefing. If you did not get a JHA briefing, ask your supervisor.
Pay attention to the large overhead screen periodically as it contains valuable information.
THINK SAFE & WORK SAFE!
The emergency telephone number is 911.
Employees are required to report the quantities completed by them accurately to the prefab supervisor each day. Employees are expected to know the pace they are to be produced for each item they are working on. If you do not know for that day, ask the prefab supervisor.
Employees are expected to log into and out of WorkMax for each specific project, they are working on.