top of page

Titan Prefab Shop

GENERAL INFORMATION:​​​

9612 Titan Park Circle, Littleton, CO 80125

The present work schedule is: Monday thru Friday
Start Time: 7:00 AM
Break: 8:30 AM-8:40 AM
Lunch: 12:00 PM-12:30 PM
Break: 2:00- 2:10 PM
Clean-Up: 3:15 PM
End Time: 3:30 PM

Start times are in your assigned work area with your pretask card and ready for stretch and flex and JHA briefing.

Quitting times are leaving your work area.
Pick-up is 15 minutes before quitting time & everyone helps everyone else. All tools must be returned to their case or shadow wall.


REMEMBER: WE ARE A TEAM!

If we are storing material that is not for an active prefabrication order, we are doing wrong.

Please remember A place for everything and everything in its place.

GENERAL INFORMATION:​​​


9612 Titan Park Circle, Littleton, CO 80125

The present work schedule is: Monday thru Friday

Start Time: 7:00 AM

Break: 8:30 AM-8:40 AM

Lunch: 12:00 PM-12:30 PM

Break: 2:00- 2:10 PM

Clean-Up: 3:15 PM

End Time: 3:30 PM


Start times are in your assigned work area with your pre-task card and ready for stretch and flex and JHA briefing.


  • Quitting times are leaving your work area.


  • Pick-up is 15 minutes before quitting time & everyone helps everyone else.


  • All tools must be returned to their case or shadow wall.



REMEMBER: WE ARE A TEAM!


If we are storing material that is not for an active prefabrication order, we are doing wrong.


Please remember A place for everything and everything in its place.



SPECIAL INSTRUCTIONS AND INFORMATION



All employees are required to visit this website for information updates. We will use this website to broadcast the latest information regarding weather and job-related announcements. 



PLEASE CHECK OFTEN FOR THE LATEST INFORMATION


SPECIAL NOTICES:  ​


3/15/24


​The site is open for work today​



  • There is no public Transporation to this location. 


  • There are no close locations at the Titan warehouse that would allow you to go to lunch and return in 30 minutes so please be prepared for this and bring your lunch.


  • Break facilities have been established along with coffee pot and refrigerator and microwave at the facility. 


  • ​All employees must park on the street south of the Titan of Warehouse or in the cul-de-sac to the south of the Titan Warehouse. 

  

​Thank you


PLEASE DO NOT ASSUME SITE WORK IS SHUT DOWN DUE TO WEATHER> ALWAYS CHECK HERE FOR INFORMATION OR CALL YOUR SUPERVISOR TO CONFIRM​



PLEASE BE AWARE OF SURROUNDINGS AT ALL TIMES.


EVERY 30 MINUTES, TAKE 30 SECONDS AND LOOK AROUND 30 FEET AND LOOK FOR HAZARDS



ALWAYS KNOW THE ADDRESS WHERE YOU ARE AND ALWAYS KNOW YOUR EVACUATION ROUTE OUT OF A BUILDING


CONTACT INFORMATION:


Project Manager: Serge Gregoire 720-473-3145​


Prefab Logistics: David Garner 719-640-8849


Warehouse Manager:  Nate Steele 720-646-1035


Director E and LP: Ted Smith 303-550-5292


Safety Superintendent: Todd Kreps 720-948-7842


  • If you are going to be late or absent, you must call, NOT TEXT, Serge Gregoire to let him know. 720-473-3145.


  • If you are not ready to work at start time when Serge starts the Stretch and Flex, you are not allowed to work unless you called Serge Gregoire and let him know you were running late.


  • If you do not call Serge Gregoire, an absence will be considered a No Call No Show. 


ACCIDENTS/ INJURIES


SDS SHEETS ARE LOCATED: 

________In the Shop at the Sign in Counter_______


Injuries must be reported immediately.


CALL Ted Smith 303-550-5292


If you get a voice mail, hang up and call again immediately and the phone will be answered.



JOBSITE RULES, RESTRICTIONS, PROJECT INFORMATION



​​SAFETY BALANCE OF PRIORITIES


  • We need to all remember that Safety, Productivity, and Quality are all important in order for us to complete our work and make the company profitable so that we can continue to be competitive and go home to our friends and family.


  • Each employee should be constantly evaluating what they are doing and balancing those priorities.


  • Remember: 30-30-30/ Every 30 minutes, stop for 30 seconds, look around 30 feet and be AWARE of your surroundings.



  

Safety is important and so is Quality:

  • Wear your PPE always. Vest, Safety glasses and gloves.

  • The person placing washers on the bolts is allowed to not wear gloves.

  • Clear safety glasses must be worn indoors.

  • Have hearing protection on your person so you have them if they are needed.


The forklift must honk its horn before entering or leaving the building


Anytime a new box of hardware is opened for production, the inventory must be removed and given to the supervisor so that declining inventories can be maintained accurately.


Be Aware of the forklift at all times


All persons must stay at least 3 feet away from the forklift at all times, except the operator


The operator must have a spotter when backing in tight areas. If you cannot see your spotter, stop operation immediately until you have contact with your spotter.


Be aware of vehicle traffic at all times


Every bracket gets:


  • 2 bolts, with two washers on each bolt and a nut on each bolt.


  • Be sure to check this before placing the brackets in the box.


  • If any are found to be wrong, be sure to send back to the front of the line and make it right


  • Stack brackets at the end of the table to 28 and then check them and then place them in the box.


  • You will do this four times for each box so that each box has 112 brackets.


  • Make sure that we are Tying or rubber banding the wings into the brackets so that they do not bounce out during shipping


  • All boxes must have wood supports, be metal strapped tight and have a single layer of shrink wrap around it wrapped tight.


  • Watch your fellow workers and if you see them showing signs of heat stress, say something and help them



  Report ANY unsafe conditions to your supervisor.


We will adhere to all company & safety policies, also OSHA Standards for temporary electric & general safety requirements.



  • Report ALL injuries to your FOREMAN or project supervisor IMMEDIATELY!


  • Housekeeping/clean-up will be required by ALL employees on a daily basis.


  • Everything must be returned to its place and floors swept and the outside entrance area swept.


  • The printer and large screen must be covered, and all tables cleared and organized. 


  • Each employee will have a current pre-task card on their person at all times while on duty and the corporate challenging policy will be followed.


  • At the end of each shift or task, all trash must be picked up and thrown away, all tools must be returned to their case or their shadow wall. NO EXCEPTIONS.


  • All floors swept, all trash cans emptied, and the back area picked up and swept up.


  • The kitchen wiped down and the coffee pots turned off and placed in the dishwasher and the dishwasher ran. 


  • All tools must be returned to their storage location and put back in their cases. 


  • Safety glasses and warning vests are to be worn at all times on the job site.


  • 100% natural fiber clothing is recommended, and sleeves must go to at least the elbow. 


  • Footwear must be sturdy work boots.


  • All employees must park on the street south of the Titan of Warehouse or in the cul-de-sac to the south of the Titan Warehouse. 



ALL ENERGIZED WORK MUST BE DONE BY QUALIFIED PERSONNEL AFTER RECEIVING WRITTEN APPROVAL FROM ALL OF THE FOLLOWING:

     Superintendent

     Project Manager

     Department Director

     Director of Education and Loss Prevention



  • Keep personal tools on-site or in gang boxes at your own risk.


  • Your personal tools are not covered by E Light's insurance; we recommend you take your personal tools home with you each night.


  • All company-supplied tools need to be returned to carrying cases before being placed in the gang box for storage each day.


  • All cleaning tools, items and equipment must be returned to the designated location anytime they are not in use. 


  • It is everyone's responsibility to keep the area clean, trash cans emptied, floors swept and material in an organized manner. 


  • Do everything, even the smallest task with pride and make sure you complete your tasks. 


  • Stretch and Flex shall be conducted before each work shift.


  • There is a place for everything and everything has its place. You are responsible for putting everything back in its place when you are done with it. 


  • Do not leave empty or partially full bottles of water laying around. 


  • Do not do work assigned by you without a JHA briefing. If you did not get a JHA briefing, ask your supervisor. 


  • Make sure that you have your pre-task card on your person at all times and that you challenge any person entering your work area that was not in your morning JHA briefing. 



THINK SAFE & WORK SAFE!


The emergency telephone number is 911.



  • Employees are required to report the quantities completed by them accurately to the prefab supervisor each day.


  • Employees are expected to know the pace they are to be produced for each item they are working on. If you do not know for that day, ask the prefab supervisor. 


  • Employees are expected to log into and out of WorkMax for each specific project, they are working on. 




Project Gallery